The contractor, Tapani,
will not work on Memorial Day (Monday, May 27th), so construction will be
Tuesday through Friday (May 28-31).
On 8th St, the new waterline that
has been installed from Commercial to Franklin is expected to be put into
service. Also next week, Century Link will be working on removing/relocating a
telephone vault at the intersection of 8th St and Exchange to allow installation
of the new sewer and storm pipe.
Tapani is expected to finish the
final stretch of storm pipe installation from Jerome to Kensington on
10th St next week. Concrete installation of curbs and intersection
corner ramps is expected to be done over the next couple weeks on 10th St.
Preparations for the pipe bursting
and slip-lining on 9th Street from Marine Drive north to the Columbia River have
begun with the primary effort scheduled for next week. On Tuesday or Wednesday,
an entry pit will be dug on the south side of Marine Drive on 9th Street. During
this construction, it will be necessary to close one lane of traffic on Marine
Drive at 9th Street and close 9th Street entirely from Commercial St to Duane
St, which is expected to take 4 to 7 days. The actual pipe bursting operation is
expected to take 4-6 hours and is currently scheduled for Thursday, May 30th.
During the pipe bursting process, Commercial Street will be reduced to one lane
of traffic from 7th Street to 10th Street.
PROJECT SCHEDULETapani has provided the following schedule of anticipated work for the coming weeks:
- Construction on 8th St between Commercial and Franklin will continue through mid-June. 8th St will be closed to through traffic in this area.
- 8th St and Exchange intersection will be closed through next week.
- Intermittent intersection closures on 8th St at Franklin may be necessary.
- Construction on 10th St will continue from Jerome to Kensington. 10th St will be closed in this area.
- Intermittent intersection closures on 10th St at Jerome and Kensington may occur over the next week.
- Construction to begin on Exchange between 10th St and 11th St as early as Tuesday.
- Construction on 11th St from Exchange to Franklin may begin at the end of next week.
- Pipe bursting and slip-lining preparation and operation on 9th St will likely begin Tuesday.