Project Update on the City of Astoria 11th St CSO Separation project.

The contractor, Tapani, is making steady progress on the 8th St and Commercial intersection that is still expected to be open to traffic by Monday, April 22nd.

PROJECT SCHEDULE
Tapani has provided the following schedule of anticipated work for the next week:
  • Crews will continue work within the 8th St and Commercial intersection.
  • Construction will begin on 8th St between Commercial and Duane. The intersection of 8th and Duane will remain open while the intersection of 8th St and Commercial is closed to traffic.
  • Construction on 10th Street between Duane and Exchange is expected to be completed today. A single traffic lane will be restored by tonight and be open through the weekend.
  • Construction on Exchange between 9th and 10th Streets will begin early next week. Intermittent traffic delays and minor road closures will be necessary on Exchange Street, but alternative routes will be available.
  • Construction may begin on 10th Street between Irving and Jerome towards the end of the week (April 18-19). The intersection of 10th and Irving will need to be closed for one day during this construction. The date of this closure is unknown at this time. Intermittent traffic delays and minor road closures will be necessary on 10th St during this construction, but alternative routes will be available.
NW Natural is relocating gas lines within the project area. They are currently working on Exchange at 8th St and 9th St.
 
The project website can be accessed via this link: http://projects.astoria.or.us/