7TH ST. & MARINE DR. STORM DRAIN PIPE REPAIR PROJECT IN ASTORIA

Lovett, Inc., contractor for the City of Astoria 7th Street & Marine Drive Pipe Repair Project, is scheduled to begin operations on Monday, December 5, 2011. They will be repairing a damaged storm drain pipe under Marine Drive at 7th Street.
Work for this project is expected to last for two weeks, through Friday, December 16th. Construction activity will be taking place between Bond Street and Astor Street along 7th Street.
All schedules are subject to change in the event of unfavorable weather conditions. No parking at these locations will be allowed. Citizens should be prepared for short traffic delays and street closures. If you have questions please call Astoria Public Works at 503-338-5173.